Author ProfileAbstract
The design of structures for a long time use represents a big challenge
in the rock mechanics and tunneling works. The water supply of the
Pirtaghi Dam reservoir-pumping power plant in Iran is provided by the
twin tunnels. Since the Pirtaghi dam site is located in an
earthquake-prone area, it will probably experience earthquakes in its
lifetime. So, in this project, the steady-state of the support system of
the twin tunnels of the water supply of the Pirtaghi power plant under
likely earthquake and static loading is evaluated by a 3D numerical
modeling. The results show that the system is capable to guarantee
stability against seismic loads.27 Aug 2021Submitted to Engineering Reports 30 Aug 2021Submission Checks Completed
30 Aug 2021Assigned to Editor
03 Sep 2021Reviewer(s) Assigned
15 Oct 2021Editorial Decision: Revise Major